BC May Shrink Hobart Lake Pipe

June 18, 2014

The Barnes County Water Resource District might shrink a pipeline for a Hobart Lake flooding fix from 26 inches to 24 inches to deal with objections from a nearby property owner. Bruce Anderson, one of the district managers, told Barnes County commissioners Tuesday that a 24-inch pipe would cost about $689,000 to install, contrasted with $819,000 for a 36-inch pipe, but it would likely take two years to decrease water levels five feet, versus one year with a 36-inch pipe. More in Wednesday's issue of the Times-Record.